Command Center

Thursday, March 26, 2026Good morning, Connor.

2 urgent · 2 action items · 3 agents active

5

Active Projects

$23.5M total contract

8

Open COs

$215K pending value

10.9%

Avg Margin

Across portfolio

71%

Daily Log Rate

3 of 5 projects compliant

Project Snapshot

ProjectContractCost to Date% CompleteMarginSchedulePM
Meridian Office Park$6.2M$4.1M
68%
11.2%On TrackMike Torres
Cascadia Retail Center$3.8M$1.8M
45%
-4.7%Cost FlagSarah Whitfield
Harborview Warehouse$4.5M$3.7M
82%
10.8%On TrackMike Torres
Eastside Medical TI$1.9M$380K
20%
11.1%On TrackDave Chen
Riverside Distribution$7.1M$3.9M
55%
9.4%Schedule FlagSarah Whitfield

Task Board

4 open · 1 assigned to you · 1 in progress

PCO-2024-031 Overdue — Cascadia Retail Centerhigh

Structural steel CO ($42,800) awaiting owner signature. 12 days past deadline.

Change Order
||CO Agent31d
Cascadia Retail Center — Cost Overrun Alerthigh

Project cost-to-date $4.92M vs $4.7M budget. 4.7% over.

Financial
||Meeting Intelligence Agent3d
Riverside Distribution — Schedule Slippagemedium

Mechanical rough-in 8 days behind. Cascading risk to drywall phase.

Schedule
||CO Agent2d
HH2 Payroll Submittals — 3 Pendingmedium

Weekly certified payroll for Cascadia, Eastside Medical, Riverside not submitted.

Compliance
||CO Agent1d

Atlas

Recent Activity

CO AgentDrafted change request PCO-2024-031 — Cascadia Retail, $29K

22 min ago

Connor CodyMarked "Submit PCO-2024-028" as Done

1 hr ago

Meeting Intelligence Agent3 action items from Riverside owner email — assigned to Connor Cody

1 hr ago

Submittal Agent2 submittals created in ACC — Cascadia and Riverside

2 hrs ago

Jonathan LiuUpdated status on Cost Overrun Alert to In Progress

2 hrs ago

CO AgentGenerated 3 commitment CO documents — ready for download

Yesterday

Andrew HayesClosed payroll compliance task for Eastside Medical

Yesterday